NEW QUESTION NO: 9
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?
A. Risk Register
B. Follow-on action recommendations
C. Issue Register
D. Lessons Report
Answer: D
NEW QUESTION NO: 10
HOTSPOT
The project has a cost tolerance of +5% I 5%, of which stage 2 has a tolerance of +£45k 1-£45k.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Hot Area:

Answer:

NEW QUESTION NO: 11
Which management product defines the detailed nature, purpose and function of a product?
A. Product Description
B. Quality Register
C. Project Product Description
D. Plan
Answer: A
NEW QUESTION NO: 12
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term

A promotional calendar as a free Christmas gift - would target current and prospective customers and

the benefits would last into a second year
A series of television and press advertisements was too expensive

A direct mail shot to all customers - benefit would be short term

Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Which 2 statements should be recorded under the Costs heading?
A. The new company logo is estimated to cost £4k.
B. 10 further orders with an average profit of £2k will deliver a benefit of £20k in the first year.
C. The project will be funded from the business marketing budget
D. Project costs are estimated to be a total of £26.5k.
E. The MNO marketing budget this year is £120k.
Answer: C,D
NEW QUESTION NO: 13
HOTSPOT
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff.
This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.
Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:

Answer:

NEW QUESTION NO: 14
Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality method?
A. Continued business justification
B. Manage by stages
C. Focus on products
D. Tailor to suit the project environment
Answer: C
NEW QUESTION NO: 15
If Project tolerances were threatened, who needs to be notified?
A. Executive
B. Project Board
C. Project Manager
D. Corporate or Programme Management
Answer: D
NEW QUESTION NO: 16
Which of the following activities is NOT an action of preparing for planned closure?
A. Update the project plan with actual
B. Confirm project has delivered what is defined in Project Product Description
C. Request a product status account
D. Update the Project Management Team
Answer: D
NEW QUESTION NO: 17
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company logo

Selected photographs- 12 professionally-produced photographs, showing different members of staff

Selected paper and selected envelope - for printing and mailing the calendar

Chosen label design - a competition to design a label will be held as part of this project

List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments

Confirm compliance with the Data Protection Legislation

Create a design for each month - this will be done by the internal creative team

Select and appoint a professional photographer

Gather photograph design ideas from previous project and agree photographic session schedule

Prepare a production cost forecast

Select paper and envelope.

Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs

Hold the label design competition and choose the label design

Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +
£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?
A. All of the project level time tolerance can be allocated to stage 2.
B. Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.
C. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.
D. There can be no time tolerances for any of the stages.
Answer: A
NEW QUESTION NO: 18
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the selected service provider?
A. The selected service provider should be located locally.
B. External consultants are to assist in the creation of the SLA.
C. Any changes to the SLA must be managed through formal change control.
D. The SLA must extend for the full duration of the service contract.
Answer: D
NEW QUESTION NO: 19
Which of the following statements is NOT correct?
The Learn from Experience principle suggests that lessons should be actively sought...
A. As the project progresses
B. When Starting a Project
C. As the project closes
D. When Initiating a Project
Answer: D